A dispute was heading for a large and costly legal wrangle over what constituted "usable space" within our client’s large data centre property. Usable space is a critical consideration when installing technological equipment that once installed in unlikely to be moved or changed for up to 20 years and longer.

What we did. We used advanced digital surveying and scanning technologies to determine to a high degree of accuracy that there was 26% less "usable space" than had been contracted for. Once agreed, our client received over £10,000 of back rent discount and a considerable saving going forward.

Data Centre Dispute Resolution - fly through model
This "fly through" model was used in the adjudication
and subsequently for space planning and optimisation.